H-215How-to · 7 min read
How to run a house build and hand it over
Build & handover follows a house from the signed quote to the keys. Your contractor logs the site from their phone, your client approves and checks the fixes on their link, and you hand over a PDF pack at the end.
Build & handover (houses): on paid plans
All docs
1. Set up the build
- Save the project to the cloud and price the quote (Main menu › Output › Estimate & quotation…). The build's stages and payments come from it.
- Open Main menu › Output › Build & handover… and press Set up from the quote. You get the usual house stages, from foundations to fixtures, each with its share of the quote, and a payment schedule with a 10 % advance.
- Add planned dates to the stages and change the payment shares if your contract differs. The shares must add up to 100 %.
2. Give the contractor and the client their links
- Open Share and make a Contractor link and a Client link. Neither needs an account.
- The contractor's link opens the drawings and, on a phone, the Site sheet in the walk-through: site photos, new snags, snags to fix, and moving stages along. It never shows payments or approvals.
- The client's link shows the drawings, comments and Approvals, and on a phone lets them report snags and verify fixes.
3. On site
- The contractor opens their link on a phone and walks the house. A photo or a snag is pinned where they stand, on the right storey.
- Photos are shrunk on the phone and uploaded at once; with no signal they wait and retry.
- When a snag is fixed they press Fixed with an after photo. You get an email, and the client sees it under To verify.
- Finishing a stage marks its payment due, and you get an email to send the bill. Mark payments Invoiced and Paid by hand.
4. Approvals
- In Approvals, pick what to approve (the drawings, the quotation, a stage or the handover), add a note and press Ask for approval. Nuvie freezes the last saved version.
- The client approves or declines on their link, typing their name. You get an email either way, with their reason if they declined.
- If the drawings or the quote change after an approval, it shows changed since. Ask again.
5. Hand over
- Clear the snags: the header's Handover box says how many are still open or waiting to be verified.
- Press Handover pack. The PDF has the drawings as built (plan, electrical, plumbing per storey), the stages and their dates, every snag put right with before and after photos, the approvals, and the brands the quote was priced with.
- Its last page, Connect your home, takes the owner through pairing the plan with Home Assistant, with QR codes.